| Month | Worked | Days worked | Tasks done | Planned | Spent on tasks |
|---|---|---|---|---|---|
| November 2026 | 60h 58m | 8 | 36 of 37 | 57h 25m | 60h 30m |
| October 2026 | - | - | - | - | - |
| September 2026 | - | - | - | - | - |
| August 2026 | - | - | - | - | - |
| July 2026 | - | - | - | - | - |
| June 2026 | - | - | - | - | - |
← 2026-11-24 2026-11-25 (today) 2026-11-26 →
0 of 1 tasks done · planned 0h 00m · spent on tasks 0h 00m
| Priority | Task | Estimate | Spent | Status | Result and updates |
|---|---|---|---|---|---|
| ✥1 | T-0176 Integrate with the website and the licensing portal Added by boss (moved from 23 Nov) Integrate the system with the website and with the web licensing portal that Markus is building. Deliverable: The system works from the website and inside the licensing portal. |
- | 0h 00m | Not started | No result yet |
Tasks you added. Mikelis Trekse does not see them until they are put into the plan. Drag a task here to park it, or drag a parked task onto the plan to hand it over.